Case study · Primary dry gas seal hang-up due to oil contamination
DGS hang-up · Fault mode
| Service | Mixed Refrigerant |
| Seals | Tandem dry gas seals |
| Primary vent | Differential pressure across a needle valve, flow |
The rotor ring turns on the shaft sleeve. The stator ring runs a few microns from it, held off by the seal gas film.
The spring pushes the stator toward the rotor, and the dynamic gasket lets it slide axially to follow the shaft. A small, steady leak passes to the primary vent.
DGS hang-up · Anomaly identification · The rule
Dp differential pressure, F flow, H and L standard high and low, Hh and Ll critical high and low.
Primary vent flow and the differential pressure across the needle valve come from separate transmitters. Both must read high, so one drifting transmitter cannot raise the event.
The third test is the percentage difference in needle valve differential pressure between the two seals. Suction pressure and speed move both seals together. A seal problem moves one.
The fourth test is the percentage difference between the actual and machine learning model predicted needle valve differential pressure. The model is trained on ‘good’ data and account for normal changes from speed or supply pressure variations
Cases 1 to 6 test the critical limits. Cases 7 to 13 test the standard limits and fire earlier, at lower priority, so the site is warned before the event escalates. Case 14 is a flow-only catch-all.
DGS hang-up · Anomaly identification · The data
Four and a half hours of primary vent data from the NDE seal, replayed at speed.
DGS hang-up · Alert · What was sent
Between 09:21 AM CT and 12:13 PM CT on DD-MMM-YY, the following were detected on the NDE primary dry gas seal of the MR Compressor:
Leakage rose on the NDE seal only and followed a change in rotor axial position. This is indicative of the NDE primary seal stator ring hanging up.
Recommendations
Each capsule is one occurrence of the event on this asset, so recurrences read on one line.
DGS hang-up · Execution and result
Medium priority, on the standard limits.
Outage work order created.
Multiple recurrence detected with a gradual increase in primary vent differential pressure excursions during rotor axial movements.
DGS cartridge replaced.
Oil contamination confirmed on the primary seal.
| Diagnosis | Confirmed on disassembly |
| Found | Oil contamination on the primary seal |
| Action | DGS cartridge replaced in a planned outage |
| Lead time | > 9 months |
| Unplanned downtime | None |
| Value | One or more vented trips avoided. Unscheduled outage for DGS replacement avoided. |